Roofing estimate template: every line item for a re-roof

Roofer standing on a partly stripped shingle roof above a brick house with a ladder
Photo: Zohair Mirza on Unsplash (Unsplash License)

A roofing estimate template for a residential re-roof needs five parts: the job header, the measured quantities with a waste factor, the line items (tear-off, decking allowance, underlayment, ice and water, drip edge, starter, shingles, ridge, flashing, vents, pipe boots, dump fees, permit and labor), the terms (warranty, payment schedule, exclusions) and an expiry date. The full template is below, with a worked example. Alvin fills it in from the measurement report and your price sheet, and holds the draft for you to review.

On this page
  1. What a roofing estimate template must include
  2. The line items, section by section
  3. Waste factor and the decking allowance
  4. Worked example: a 25-square re-roof
  5. Terms: warranty, payment schedule, exclusions, expiry
  6. Common roofing estimate mistakes
  7. What Alvin handles and what stays with you
  8. Questions
Definition A roofing estimate is a written price for a defined scope of work on one roof. It lists what will be removed, what will be installed, in what quantity, at what price, and under what terms. A square is 100 square feet of roof surface.

What a roofing estimate template must include

Before the line items, the header has to make the document stand on its own. A homeowner will forward it to a spouse, a lender or an insurance adjuster, and none of them were on the roof with you.

  • Your company: name, license number where one is required, phone, email.
  • The customer and property: name, job address, date of inspection.
  • The roof: measured squares, pitch, number of existing layers, source of the measurement (report or hand measure).
  • Estimate number, date and expiry date.
  • Scope summary: two or three sentences in plain words, such as "Remove one layer of shingles and replace with architectural shingles on all slopes of the main house. Detached garage not included."
Watchers panel listing two unpaid invoices, the Smith estimate going stale (Estimate 1042, HDZ upgrade, sent 6 days ago, no reply) and an unscheduled gutter job, each with Acknowledge and Resolve buttons.
Example: Alvin's watchers flag the Smith estimate going stale six days after it went out with no reply (demo data).

The line items, section by section

Copy this table into your estimating tool or spreadsheet. Keep the order: it follows the job from tear-off to cleanup, which is how a homeowner pictures the work.

Scroll sideways to see every column.

Line itemUnitWhat to write on the line
Tear-offSquareNumber of layers removed, down to the deck
Decking allowanceSheetSheets included in the price, and the price per extra sheet
UnderlaymentSquareType (synthetic or felt) and where it goes
Ice and water shieldRoll or linear footLocations: eaves, valleys, around penetrations
Drip edgeLinear footEaves and rakes, color
Starter stripLinear footEaves, and rakes if you run it there
ShinglesSquareManufacturer, line and color, quantity with waste
Hip and ridge capLinear footProduct, matched to the shingle line
FlashingLinear foot or eachStep, counter, chimney and wall flashing: new or reused, and say which
VentilationLinear foot or eachRidge vent or box vents, intake if you are adding any
Pipe bootsEachCount and type
Dump feesLump sumDumpster or trailer, haul-off included
PermitLump sumWho pulls it and whether the fee is included
LaborSquareInstallation, with any steep or two-story charge shown
CleanupIncludedMagnetic sweep, gutters cleared, property protection

Some shops show a price per line, others quantities and one total. Either works if the quantities are there.

Waste factor and the decking allowance

These two lines cause most of the arguments after the job, so write them carefully.

Waste factor. Shingles are cut at hips, valleys and rakes, so you order more than the measured area. A simple gable needs less extra than a cut-up hip roof. State the measured squares and the ordered squares separately, for example "25 squares measured, 12% waste, 28 squares ordered". Most measurement reports suggest a waste range for the roof they measured.

Decking allowance. Nobody can see rotten decking until the shingles are off. Include a set number of sheets in the price and give the price for each sheet beyond that. Then the homeowner has already agreed to the rate before the crew finds the soft spot over the bathroom.

Worked example: a 25-square re-roof

All numbers below are examples to show the layout. Use your own price sheet.

Scroll sideways to see every column.

Line itemQuantityExample priceExample total
Tear-off, one layer25 sq$60$1,500
Decking allowance (extra sheets $85 each)3 sheets$85$255
Synthetic underlayment25 sq$28$700
Ice and water shield, eaves and valleys4 rolls$110$440
Drip edge240 ft$2.50$600
Starter strip240 ft$1.50$360
Architectural shingles (12% waste)28 sq$135$3,780
Hip and ridge cap60 ft$6$360
Chimney and wall flashing, newLump sum$450
Ridge vent40 ft$9$360
Pipe boots4$45$180
Dump feesLump sum$550
PermitLump sum$250
Installation labor25 sq$120$3,000
Example total$12,785

Example payment schedule for this job: $1,285 at signing, $5,750 when materials are delivered, $5,750 at completion. The three payments add up to the total, and the estimate says what "completion" means (final cleanup done, not the day the last shingle goes on).

Terms: warranty, payment schedule, exclusions, expiry

  1. Warranty terms. State your workmanship warranty in years and what it covers. Name the manufacturer warranty separately and say whether you will register it. See how roof warranty registration works.
  2. Payment schedule. Amounts or percentages tied to events: signing, delivery, completion. List the payment methods you take.
  3. Exclusions. Write what is not in the price: decking beyond the allowance, gutters, skylight replacement, fascia or soffit repair, interior damage, satellite dish realignment, code upgrades found after tear-off.
  4. Change orders. Say that extra work is priced and approved in writing before it is done.
  5. Expiry date. Shingle prices move. Many shops hold a price for 15 to 30 days; pick a window you can honor and print the date.

Contract terms, deposit limits, license disclosures and cancellation notices vary by state and city. This article is general information, not legal advice. Check the rules that govern your business before you use any template.

Common roofing estimate mistakes

  • No decking rate. The price per extra sheet gets negotiated on the driveway with the roof open.
  • "Flashing as needed." Say new or reused, and where. Reused flashing is a common source of callbacks.
  • Measured squares shown as ordered squares. The waste goes missing and so does the margin.
  • Old prices. The estimate was built from a price sheet nobody updated after the last supplier increase.
  • No expiry date. A homeowner calls back four months later and expects the same number.
  • No follow-up. A good estimate still needs a nudge. See roofing estimate follow-up for a schedule.

What Alvin handles and what stays with you

Alvin doesYou do
Reads the measurement report and fills the template with quantities, including wasteInspect the roof and decide the scope
Prices each line from your price sheet and flags lines with no priceSet and update the price sheet and your margins
Drafts the estimate in your CRM or as a document with your brandReview, adjust and approve before anything goes to the customer
Sends the approved estimate from your own email, with a receipt of who approved itAnswer scope and price questions from the homeowner
Checks for stale estimates and drafts follow-ups for approvalDecide on discounts and when to walk away

To check squares and bundles before you price a roof, use the free roofing square calculator.

Frequently asked questions

What should be included in a roofing estimate?

A roofing estimate should include your company and license details, the property address, measured squares and pitch, each line item with a quantity, the total, warranty terms, a payment schedule, exclusions and an expiry date. The line items for a re-roof are tear-off, decking allowance, underlayment, ice and water shield, drip edge, starter, shingles, ridge cap, flashing, vents, pipe boots, dump fees, permit and labor.

How much waste factor should a roofing estimate use?

It depends on the roof. A simple gable roof needs less extra material than a hip roof with many valleys and dormers. Use the waste range on your measurement report as a starting point, adjust for what you saw on site, and show measured and ordered squares on separate lines.

What is a decking allowance on a roof estimate?

A decking allowance is a set number of sheets of roof decking included in the price, plus a stated price for each extra sheet. Rotten decking cannot be seen until tear-off, so the allowance sets the rate in advance and avoids a dispute mid-job.

How long should a roofing estimate be valid?

Many roofing companies hold an estimate for 15 to 30 days because material prices change. Choose a window you can honor with your supplier's current pricing and print the expiry date on the estimate.

Is a roofing estimate the same as a contract?

Not always. An estimate states a price for a scope; a contract is the signed agreement with the terms your state requires. Many shops combine them in one document with a signature block. Check your state's rules for home improvement contracts.